SHELL GAS BULGARIA

1.  Microprocessor system for vizualization and control

Employer: SHELL GAS BULGARIA
Project: Gas filling plant in Benkovski, Plovdiv district
Subproject: Microprocessor system for vizualization and control
Design: For performance of conventional and microprocessor part
Main contractor: Start engineering Co.
Kinds of activities: Design (hardware and software), installation and commissioning
Performance: Finished in 1999

Short description of the project:

The project was performed by specialists of Start engineering Co. branch Sofia by preliminary design of Kvaerner Process (Provence) SNC and specific requirements of the employer.

The microprocessor control system consists of programmable logic controller (PLC) SIMATIC S7-300 of SIEMENS and operator’s station (OS) based on a personal computer (PC) Packard Bell. The connection between them is digital serial interface by RS485 standard with conversion in the ÐÑ by MPI card.

 The PLC is supplied by 24V DC from redundant rectifier 40À, and the PC – from 220V, 50Hz. The 220V, 50Hz supply of the rectifier and the PC is from UPS of Merlin Gerin

 The application software for the controller is realized by means of the programming language STEP 7 of SIEMENS, and the application software for the operator’s station – by means of the vizualization software WinCC of SIEMENS.

 

System configuration


 
  Main operating screen

  Fire fighting system screen

  Download in PDF
SHELL GAS BULGARIA - Gas filling plant in Benkovski, Plovdiv district:

Microprocessor system for vizualization and control

  Download Adobe Acrobat Reader (needed to open the PDF document)
2.  Upgrade and revision of conventional and microprocessor part in connection with Extension I stage
Employer: SHELL GAS BULGARIA
Project: Gas filling plant in Benkovski, Plovdiv district
Subproject: Microprocessor system for vizualization and control
Design: Upgrade and revision of conventional and microprocessor part in connection with Extension I stage
Main contractor: Start engineering Co.
Kinds of activities: Design (hardware and software), installation and commissioning
Performance: Completed in 2001

Short description of the project:

The project was executed by specialists of START ENGINEERING Co. BRANCH SOFIA by instruction of MONTAZHPROEKT OOD
.

The originally erected tank for 200 m3 propane-butane has changed its designation – only for propane. Two new tanks for propane-butane 400 m3 each were erected along with the relevant piping and valve structure (including an option for blending).

The microprocessor control system has changed. The CPU is now redundant and operates in warm redundancy mode by means of SW-Redundancy V1.1. software. Besides this, by recommendation of START ENGINEERING JSCo.  the Operator’s station was made redundant (SHELL GAS purchased another licence for WinCC Runtime) and this proved quite appropriate in a certain critical moment (failure of the first Operator’s station).

System configuration after expansion (Redundancy CPU)

Main monitoring screen                    Control window                        Other control window

       PLC cabinets                                PLC cab. interior                         Techn. assistance

  Download in PDF
SHELL GAS BULGARIA - Gas filling plant in Benkovski, Plovdiv district:

Upgrade and revision of conventional and microprocessor part in connection with Extension I stage

  Download Adobe Acrobat Reader (needed to open the PDF document)
 
3.  Upgrade and revision of conventional and microprocessor part in connection with Extension I stage II phase
Employer: SHELL GAS BULGARIA
Project: Gas filling plant in Benkovski, Plovdiv district
Subproject: Microprocessor system for vizualization and control
Design: Upgrade and revision of conventional and microprocessor part in connection with Extension I stage II phase
Main contractor: Start engineering Co.
Kinds of activities: Design (hardware and software), installation, startup and commissioning
Performance: 2004

Short description of the project:

The project was executed by specialists of START ENGINEERING Co. BRANCH SOFIA by task assignment  of MONTAZHPROEKT OOD.

A third LPG pump and pressure transmitter for it are mounted. Five new flow transmitters are mounted: 1 after the propane tank, 2 at Road Tank Loading Facility (liquid and gas phase) and 2 at Railway Tank Unloading Facility (liquid and gas phase). A pressure transmitter is mounted at the Railway Tank Unloading Facility as well. The new transmitters communicate with the control system via PROFIBUS PA. The interface to PROFIBUS DP is made by two DP/PA couplers. The purpose of this additional equipment is to provide more complete and timely information on the material flows in the station, as well as to improve the control and safety of the facilities.

System configuration after I stage II phase extension

 The main view screen now looks like this:

Main screen

Changes in the other screens for view and printout, as well as in the control windows are made. A new common screen is added - for monitoring the flow meters:

Flow meters

       PLC cabinets                                PLC cab. interior                         Techn. assistance
 

  Download in PDF
SHELL GAS BULGARIA - Gas filling plant in Benkovski, Plovdiv district:

Upgrade and revision of conventional and microprocessor part in connection with Extension I stage II phase