| Employer: | | | Project: | Union Miniere Pirdop Med - Pirdop | | Subproject: | Reconstruction of melting furnace with fluidized bed and waste-heat boiler 1999 - 2000 | | Design: | According to existing design | | Main contractor: | “Start Engineering” JS Co. | | Subcontractors: | | | Kinds of activities: | Delivery and fabrication of electric panels, installation works, adjustment and starting up of the technological facilities and control loops | | Performance: | Completed in 2000 |
|
Short information concerning the project:
The design was performed by specialists of "Start Engineering" JS Co. - Sofia branch.
"Start Engineering " JS Co. - Sofia branch is main contractor of the Electrical installation and Starting up and adjustment works of all technological facilities, inspection and adjustment of control and visualization loop - 668 pcs.